Update from the Contractor - 7th July 2006

Sri Vinayagar Vidyalayam, Onthachimadam, Batticaloa

Progress of work

Block – A:
(Single Story Classrooms)
Brick work up to Roof level completed.

Block – B:
(Two Storied Classrooms)
Brick work up to 1st floor slab completed
Shuttering for 1st floor slab completed
Reinforcement work for the slab is in progress
Concrete for the 1st floor slab will be done by next Thursday (13/07/2006)

Block – C:
(Part of Upper School & Administration Building – 60% of C&D)
Brick work up to 1st floor slab completed
50% concrete for the 1st floor slab completed
Brick work above 1st floor slab is in progress

Block – D:
(Part of Upper School & Administration Building – 40% of C&D)
Foundation Completed
90% Brick work up to 1st floor slab completed and is in progress

Overall Progress: Good
Security Situation: Normal (2 – 3 incidents per day)
Weather: Warm and windy