Monday, April 17, 2006

Construction Underway


Images of construction work in progress as of 10th April 2006

Construction Underway in Batticaloa School


Ground Floor Columns & Brick work-50% in Wing A of 2 storeyed block. Column Foundations 50% in Wing B.

Schools Update!

Work is progressing at a fair pace. Admin Block column foundations almost complete.

Admin Block - Columns & Brick work - 40%