Thursday, February 15, 2007

February 2007 - Progress Report

"The progress of work continues at a satisfactory pace. Admin Block- Wing-A – 1st Fl. Col.s & Bk. Work- 100%. Admin Block- Wing-B –G. Fl. Plaster-70%, F. Fl. Columns, Bk. Work-100%, Single Storeyed Block- 2-Storeyed Block –No progress. Roof Trusses are being fabricated away from site at an alternate location."
"Work is progressing well and at a satisfactory pace.Admin Block- Wing-A – 1st Fl. Col.s & Bk. Work- 100%Admin Block- Wing-B –G. Fl. Plaster-70%, F. Fl. Columns, Bk. Work-100%"

0 Comments:

Post a Comment

<< Home