31 December 2006 - Year-end Report

The progress of work on the school has been quite reasonable. The Contractor has faced regular shortages of labour as the demand for both skilled and unskilled labour in the area is now quite high.Overall 60% of the work has now been completed.
Both main buildings have now been completed upto Roof Level. Additionally, the internal plastering of the first building is also almost completed.