Update from the Contractor - 7th July 2006
Sri Vinayagar Vidyalayam, Onthachimadam, Batticaloa
Progress of work
Block – A:
(Single Story Classrooms)
Brick work up to Roof level completed.
Block – B:
(Two Storied Classrooms)
Brick work up to 1st floor slab completed
Shuttering for 1st floor slab completed
Reinforcement work for the slab is in progress
Concrete for the 1st floor slab will be done by next Thursday (13/07/2006)
Block – C:
(Part of Upper School & Administration Building – 60% of C&D)
Brick work up to 1st floor slab completed
50% concrete for the 1st floor slab completed
Brick work above 1st floor slab is in progress
Block – D:
(Part of Upper School & Administration Building – 40% of C&D)
Foundation Completed
90% Brick work up to 1st floor slab completed and is in progress
Overall Progress: Good
Security Situation: Normal (2 – 3 incidents per day)
Weather: Warm and windy