Site Update from Contractor - 20th December 2006
Re: Sri Vinayagar Vidyalayam, Onthachimadam, Batticaloa
Progress of work
Block – A: (Single Story Classrooms)
1) Brick work up to Roof level – 100% completed.
2) Floor Concrete – 100% completed
3) Roof work is in progress
Block – B: (Two Storied Classrooms)
1) Brick work up to Roof level – 100% completed.
2) Floor Concrete – 100% completed
3) Soffit plastering – 100% completed
4) Internal plastering – 50% completed
5) External plastering – 50% completed
6) Electrical work – 30% completed
Block – C: Part of Upper School & Administration Building)
1) Brick work up to Roof level – 100% completed.
2) Floor Concrete – 60% completed
3) Soffit plastering – 80% completed
4) Internal plastering – 50% completed
5) External plastering – 40% completed
6) Electrical work – 30% completed
Since there were delays in our work earlier which were beyond our control, we request you to grant us an extension until end of February 2007.
Thank you very much for your cooperation.
Yours Sincerely,
VJ Engineers (PVT) LTD.
Vijay Somasundaram
Managing Director
0 Comments:
Post a Comment
<< Home