Friday, August 11, 2006

Status Report - Sri Vinayagar Vidyalayam, Batticaloa - August 2006

Progress of work

Block – A: (Single Story Classrooms)
Brick work up to Roof level completed.

Block – B: (Two Storied Classrooms)
Brick work up to 1st floor slab completed
Concrete for 1st floor slab completed
Columns above 1st floor slab up to roof level completed
Brick work above 1st floor slab is in progress

Block – C: (Part of Upper School & Administration Building – 50% of C&D)
Brick work up to 1st floor slab completed
Concrete for the 1st floor slab completed
50% Columns above 1st floor slab up to roof level completed
50% Brick work above 1st floor slab completed
50% Floor Concrete completed
50% Soffit Plastering completed
50% Internal Plastering completed
25% External Plastering completed

Block – D: (Part of Upper School & Administration Building – 50% of C&D)
90% Brick work up to 1st floor slab completed and is in progress

Overall Progress: Good

VJ Engineers (Pvt) Ltd.

0 Comments:

Post a Comment

<< Home